Journal of Petroleum Technology, Vol.48, No.4, 322-323, 1996
Brief - Multizone Subsea Completions in the DAI-Hung Field, Vietnam
The early production phase of the Dai Hung field development involved drilling and completion of five subsea wells. Owing to the complex nature of the reservoirs, selective multizone completions were installed for effective reservoir data acquisition and reservoir management. Downhole completion designs used equipment that was primarily of existing proven design, and downhole equipment was installed in a single trip. Ongoing reservoir management will be aided by use of a subsea wireline system to facilitate data acquisition.